How it runs / kominka renovation
What happens from first contact to handover
The construction itself takes two to four months, but survey and design come before it. Here is how long the whole thing takes and when money moves.
- From consultation to handover there are six steps: consultation, on-site survey, proposal, design and quote, construction, handover.
- Allow six months to a year in all, with 2–4 months for the construction itself.
- The time goes before construction: design and quote take 1–2 months.
- Consultation, on-site survey and a rough-estimate proposal are free. Charges start with design and quote.
- From consultation to the start of construction takes 3 months at the fastest, and usually about six months.